What is the statutory limit for filing a lien in Florida?

Prepare for the Florida NASCLA Contractors Exam. Study using flashcards and multiple choice questions, each with detailed hints and explanations. Ace your exam effortlessly!

The statutory limit for filing a lien in Florida is indeed 1 year from the date the work was completed or materials supplied. This timeframe is established under Florida's lien law, which allows contractors, subcontractors, and suppliers to secure payment for services rendered or materials provided. By limiting the time frame to one year, the law encourages prompt resolution of payment disputes and provides a clear expectation for all parties involved regarding when claims can be made.

Filing a lien after this one-year period can lead to denial and dismissal due to the statute of limitations having been exceeded. This provision enables property owners and contractors to maintain clarity regarding financial obligations, ensuring that claims for payment do not linger indefinitely. The other time frames provided in the options do not align with Florida's statutory requirements, making the one-year period the correct and validated choice.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy